Neoliner Origin’s ship’s log – Ep02
Non classé -Construction of the Neoliner Origin is progressing at the RMK Marine. The vessel is gradually taking shape!
✂️ 80% of the steel has been cut (equivalent to 2830 tonnes 😲).
🔧 Fabrication of blocks and pipe installation continues.
👷 The fix cargo loading ramp has been installed.
🪜 Stairs are currently being fitted on board.
⛵ With a launch scheduled for December 2024 and commissioning by mid-2025, the Neoliner Origin will herald a new era in maritime transport. It will depart from Saint-Nazaire to Baltimore, with stops in Saint-Pierre and Miquelon and Halifax (CAN).